§ 157.176 ABANDONED OR UNUSED TOWERS OR PORTIONS OF TOWERS.
   Abandoned or unused towers or portion of towers shall be removed as follows.
   (A)   All abandoned or unused towers and associated facilities shall be removed within 12 months of the cessation of operations at the site unless a time extension is approved by the Building Inspector. A copy of the relevant portions of a signed lease which requires the applicant to remove the tower and associated facilities upon cessation of operations at the site shall be submitted at the time of application. In the event that a tower is not removed within 12 months of the cessation of operations at a site, the tower and associated facilities may be removed by the village and the costs of removal assessed against the property.
   (B)   Unused portions of towers above a manufactured connection shall be removed within six months of the time of antenna relocation. The replacement of portions of a tower previously removed requires the issuance of a new conditional use permit.
(1981 Code, Art. XIII, l) (Ord. passed 12- -1986)