(a) Fees for a sewer permit shall be in accordance with the following schedule.
Between Curb and Street Side Line Only | Between a Point in the Pavement and Street Side Line | |
For each 6-inch or smaller sewer connection | $6 | $8 |
For each 8-inch sewer connection | $8 | $10 |
For each 10-inch sewer connection | $10 | $12 |
For each 12-inch or larger sewer connection | $12 | $14 |
(b) In the event that it is necessary to construct, add to, alter or repair more than one sewer connection, each connection shall be considered as separate and shall require a separate permit and fee, except that, where properties are served by a system of separate storm and sanitary connections, one storm and one sanitary connection shall be together classed as a single connection of the size of the larger connection.
(c) In the event that it is necessary to open the street pavement for constructing, adding to, altering or repairing any sewer construction, a deposit in addition to the fee hereinabove provided shall be required to cover the cost of repaving such opening and the amount of such deposit shall be fixed by the City Engineer.
(Ord. 05-08, passed 2-19-2008)