(A) An applicant that provides wireless communications service or otherwise makes available infrastructure for wireless communications services may apply for a permit to:
(1) Locate a new wireless facility or wireless support structure;
(2) Perform a substantial modification; or
(3) Collocate wireless facilities on existing structures in the GROW-OL to the City Planner.
(B) An applicant shall demonstrate that the proposed wireless facility, wireless support structure, or substantial modification thereof complies with the requirements of the GROW-OL.
(C) Upon determination of a complete application and initial review by the Zoning Administrator, the application shall be forwarded to the City Board of Public Works and Safety for review by the City Engineering Department. The application shall also include a utility plan. The City Engineering Department shall submit a report determining technical compliance and whether there are any conflicts with existing utilities, construction plans, or other applicable regulations including, but not limited to. East Chicago Board of Public Works.
(D) The Board of Public Works shall make its recommendation and determination and forward it to the City Planner with the report from the City Engineering Department for a determination of the issuance of permits.
(Res. 02-2017, passed 1-17-2017; Ord. 17-0001, passed 2-27-2017)