§ 151.56 TEMPORARY APPROVAL OF SERVICE.
   (A)   Temporary wiring may be installed when written permission is secured from the Building Official.
   (B)   No temporary approval shall be issued for a period of more than 90 days. If necessary for temporary work to remain more than 90 days, request for such extension of temporary approval shall be made in writing by the person holding the permit.
   (C)   Upon expiration of temporary approval, such approval shall be immediately discontinued, unless approval for extension of time is obtained from the Building Official.
('90 Code, § 7-44.13) (Ord. passed 4-12-76)