§ 151.50 APPLICATIONS.
   (A)   Before beginning any work of electrical installation, construction or repair, or any changes which would increase the load, an application for a permit shall be made to the Building Official on forms furnished for that purpose, which application shall contain an accurate and detailed account of electrical work contemplated as provided for in the forms furnished. ('90 Code, § 7-44.5)
   (B)   Before starting work on installation for systems over 600 volts, a completed layout in detail shall be submitted to the Building Official. ('90 Code, § 7-44.6)
   (C)   If after obtaining a permit for electrical work it is found necessary to change or increase the load of current, an application for a permit shall be filed covering the additional work. ('90 Code, § 7-44.7)
(Ord. passed 4-12-76) Penalty, see § 151.99