§ 52.044 SEDIMENT AND EROSION CONTROL PLAN REQUIREMENTS.
   (A)   The sediment and erosion control plan shall accurately describe the potential for soil erosion and sedimentation problems likely to result from the land disturbing activity, and shall explain and illustrate the measures that are to be taken to control these problems. The plan shall conform to the requirements found in the city’s LDRs and shall include the following:
      (1)   Project description;
      (2)   A topographic map;
      (3)   All existing drainage ways;
      (4)   A general description of existing land cover;
      (5)   Stands of existing trees, as they are to be preserved upon project completion;
      (6)   Approximate limits of proposed clearing, grading and filling;
      (7)   Approximate flows of existing stormwater leaving any portion of the site;
      (8)   A general description of existing soil types;
      (9)   Location, size and layout of proposed stormwater and sedimentation control improvements;
      (10)   Proposed drainage network;
      (11)   Proposed drain tile or waterway sizes;
      (12)   Approximate flows leaving site after construction;
      (13)   The projected sequence of work;
      (14)   Specific remediation measures to prevent erosion and sedimentation run-off;
      (15)   Specific details for the construction of rock pads wash down pads;
      (16)   Proposed structures, location (to the extent possible).
   (B)   See the latest edition of the City of Easley Land Development Regulations and SCDHEC’s Storm Water BMP Handbook for a complete description of each requirement.
(Ord. 2008-06, passed 4-14-08) Penalty, see § 52.999