Sec. 10-160 Application Process: Final Development Plan.
   a.   Within six (6) months of the Plan Commission's approval of the preliminary development plan, the applicant shall file with the Plan Commission a final development plan containing in final form the information required in the preliminary plan. The Plan Commission, however, may extend for an additional six (6) months the time period for the filing of the final development plan, when adequate need is shown. The final development plan may be submitted with the preliminary development plan if the Plan Commission deems it reasonable to allow such submittal. (See Section 10-159b.)
   b.   If the final development plan deviates in a material way from the preliminary development plan, the applicant shall be required to submit a revised preliminary development plan in the same manner as the original application.
(Ord. No. 2007-33, 12-27-07)