(a) Upon approval of the Site Plan, an application for a Zoning Permit may be submitted to the Zoning Inspector for the construction of any building or improvement in conformity with the provisions of this Zoning Ordinance and the duly approved Site Plan. No construction or site improvement shall be initiated until the Site Plan has been approved and a Zoning Permit has been issued.
(b) Any site plan may be revised and such revisions shall be accomplished in the same manner as the original approval provided, however, that minor technical changes which do not substantially alter the original site plan may be authorized by concurring approval of the Mayor, Village Engineer and Zoning Inspector. One (1) year after satisfactory completion of the required improvements, the Village shall release any remaining bonds.
(Ord. 98-12. Passed 4-7-98.)