1185.06 APPLICATION PROCEDURES.
   (a)   Soil Disturbing Activities Submitting a Stormwater Pollution Prevention Plan (SWP3): The applicant shall submit two (2) sets of the SWP3 and the applicable fees to the Zoning Inspector.
      (1)   For subdivisions: After the approval of the preliminary plans and with submittal of the improvement plans.
      (2)   For other construction projects: Before issuance of a zoning permit by the Zoning Inspector.
      (3)   For general clearing projects: Prior to issuance of a zoning permit by the Zoning Inspector.
   (b)   Soil Disturbing Activities Submitting an Abbreviated Stormwater Pollution Prevention Plan (SWP3): The applicant shall submit two (2) sets of the abbreviated SWP3 and the applicable fees to the Zoning Inspector.
      (1)   For single-family home construction: Before issuance of a zoning permit by the Zoning Inspector.
      (2)   For other construction projects: Before issuance of a zoning permit by the Zoning Inspector.
      (3)   For general clearing projects: Prior to issuance of a zoning permit by the Zoning Inspector.
   (c)   Soil disturbing activities shall not begin and zoning permits shall not be issued without:
      (1)   Approved SWP3 or abbreviated SWP3;
      (2)   Installation of erosion and sediment controls;
      (3)   Physical marking in the field of protected areas or critical areas, including wetlands and riparian areas.
   (d)   SWP3 for individual sublots in a subdivision will not be approved unless the larger common plan of development or sale containing the sublot is in compliance with this regulation.
   (e)   Approvals issued in accordance with this regulation shall remain valid for one (1) year from the date of approval.
(Ord. 2019-13. Passed 6-18-19.)