1183.12 MAINTENANCE AND FINAL INSPECTION APPROVAL.
   To receive final inspection and acceptance of any project, or portion thereof, the following must be completed by the applicant and provided to the Village Engineer:
   (a)   Final stabilization must be achieved and all permanent SCMs must be installed and made functional.
   (b)   An as-built certification, including as-built survey and inspection, must be sealed, signed and dated by a professional engineer and a professional surveyor with a statement certifying that the stormwater control measures, as designed and installed, meet the requirements of the comprehensive stormwater management plan .
   (c)   A copy of the complete and recorded inspection and maintenance plan and inspection and maintenance agreement must be provided to the Village.
(Ord. 2019-13. Passed 6-18-19.)