1115.05 PERMITS ISSUED AFTER PLAT APPROVAL.
   (a)    Building or repair permits shall not be issued for any structure on a lot in a subdivision for which a plat has not been approved and recorded in the manner described herein.
   (b)    Building occupancy shall not occur until all improvements including utilities are complete, inspected and accepted in writing by the City.
   (c)    Utility improvements by the developer pursuant to the plat and subject to the provisions of Chapter 1111 shall not be deemed as finally accepted until such time as the City Engineer shall certify to the Service Director that the same are completed and have been inspected and the Service Director has accepted the same in writing addressed to the developer and bonding company or escrow agent holding the developer's bond. Such writing must indicate that the utilities have been completed, inspected and are being finally accepted by the City.
   (d)    No owner or agent of the owner of any land shall be entitled to a permit for the installation of wells and septic tanks upon any lots in a subdivision for which a plat has not been approved and recorded in the manner prescribed herein. (Ord. 55-89. Passed 7-17-89.)