§ 160.09 COLLOCATION COMPLETION DEADLINE.
   Collocation for which a permit is granted shall be completed within 180 days after issuance of the permit, unless the village and the wireless provider agree to extend this period or a delay is caused by make-ready work for an authority utility pole or by the lack of commercial power or backhaul availability at the site, provided the wireless provider has made a timely request within 60 days after the issuance of the permit for commercial power or backhaul services, and the additional time to complete installation does not exceed 360 days after issuance of the permit. Otherwise, the permit shall be void unless the village grants an extension in writing to the applicant.
(Ord. 2018-12, passed 7-24-2018)