§ 157.12 FEES CHARGED FOR BUILDING PERMIT APPLICATION AND SPECIAL USE PERMIT APPLICATION.
   (A)   Special use permit fees. These fees shall apply only to SES projects and shall supersede any other fee calculation for special use permits.
      (1)   Community solar garden is $5,000 per application.
      (2)   Commercial/large scale solar facility is $5,000 plus $35 per acre.
      (3)   This fee shall be used to cover the county’s costs incurred during the special use application review process, public hearings, and board approval of the SES including, but not limited to, internal expenses, hiring external technical experts, attorneys, or other professionals to assist with the review, meeting venues for public hearings, and all other expenses incurred by the county to ensure the application meets the requirements of this chapter. Should the actual costs to the county exceed the fee amount, the applicant shall be responsible for those costs and shall remit additional funds within 15 days written notice from the county.
   (B)   Building permit fee.
      (1)   Residential/community solar garden.
 
0-4 kilowatts (kW-dc)
$75
5-15 kilowatts (kW-dc)
$150
16-50 kilowatts (kW-dc)
$300
51-100 kilowatts (kW-dc)
$500
101-500 kilowatts (kW-dc)
$1,000
501-1000 kilowatts (kW-dc)
$3,000
1001-2000 kilowatts (kW-dc)
$5,000
 
      (2)   The building permit fee for commercial/large scale solar facility is $5,000 for the first two megawatts (MW) and $1,000 for each additional megawatt (MW).
(Res. 2019-01, passed 3-21-2019; Ord. passed 4-21-2022)