14-1-7: OCCUPATION AND USE OF IDENTIFIED FLOODWAYS:
This section explains the procedures which are to be followed to determine if a site is within a floodway and sets the minimum requirements for all development within a floodway.
This section applies to proposed development, redevelopment, site modification or building modification within a designated floodway. The designated floodway for the Des Plaines River, Prairie Creek, Farmers Creek, Willow Creek, Weller Creek, and Feehanville Ditch shall be as delineated on designated FEMA flood insurance rate maps referenced in section 14-1-2 of this chapter. Only those uses and structures will be permitted which meet the criteria in this section. All floodway modifications shall be the minimum necessary to accomplish the purpose of the project. The development shall also meet the requirements of section 14-1-9 of this chapter.
   A.   Development Permit: No person, firm, corporation or governmental body not exempted by state law shall commence any development in a floodway without first obtaining a development permit from the community development director with approval from the director of engineering.
Development in the floodway will be limited to existing developments (redevelopment) on a limited basis or as deemed as necessary by the director of engineering, and shall be limited to appropriate uses of the floodway.
      1.   Application for a development permit shall be made on a form provided by the community development director. The application shall include the following information:
         a.   Name and address of applicant.
         b.   Site location (including legal description) of the property, drawn to scale of one inch equals twenty feet (1"=20') with the limits of the regulatory floodway delineated, indicating whether it is proposed to be in an incorporated or unincorporated area.
         c.   Name of stream or body of water affected.
         d.   Description of proposed activity.
         e.   Statement of purpose of proposed activity.
         f.   Anticipated dates of initiation and completion of activity.
         g.   Name and mailing address of the owner of the subject property if different from the applicant.
         h.   Signature of applicant or the applicant's agent.
         i.   If the applicant is a corporation, the president or other authorized officer shall sign the application form.
         j.   If the applicant is a partnership, each partner shall sign the application form.
         k.   If the applicant is a land trust, the trust officer shall sign the name of the trustee by him/her as trust officer. A disclosure affidavit shall be filed with the application identifying each beneficiary of the trust by name and address and defining the respective interests therein.
         l.   Plans of the proposed activity shall be provided which include as a minimum:
            (1)    A vicinity map showing the site of the activity, name of the waterway, boundary lines, names of roads in the vicinity of the site, graphical or numerical scale of one inch equals twenty feet (1" = 20') and north arrow.
            (2)    A plan review of the project and engineering study reach showing existing and proposed conditions including principal dimensions of the structure or work, elevations using the 1988 NAVD, adjacent property lines and ownership, existing and proposed grades (spot elevations), existing and proposed elevation contours, drainage and flood control easements, location of any channels and any existing or future access roads, distance between proposed activity and navigation channel (when the proposed construction is near a commercially navigable body of water), designated floodway limit, floodplain limit, specifications and dimensions of any proposed channel modifications, delineation of basin and subbasin areas, location and orientation of cross sections, north arrow, and a graphical or numerical scale.
            (3)    Cross section views of the project and engineering study reach showing existing and proposed conditions including principal dimensions of the work as shown in plan view, existing and proposed elevations, normal water elevation, 10-year frequency flood elevation, 100-year frequency flood elevation, and graphical or numerical scales (horizontal and vertical).
            (4)    A soil erosion and sedimentation control plan for disturbed areas, including outfalls. This plan shall include a description of the sequence of grading activities and the temporary sediment and erosion control measures to be implemented to mitigate their effects. This plan shall also include a description of final stabilization and revegetation measures, and the identification of a responsible party to ensure postconstruction maintenance.
            (5)    A copy of the designated floodway map, marked to reflect any proposed change in the regulatory floodway location.
         m.   Any and all other local, state and federal permits or approval letters that may be required for this type of development.
         n.   Engineering calculations and supporting data shall be submitted for hydrologic and hydraulic analysis as well as all sediment control and erosion protection measures showing that the proposed work will meet the permit criteria of subsection B of this section.
         o.   If the designated floodway delineation, base flood or 100-year frequency flood elevation will change due to the proposed project, the application will not be considered complete until IDNR/OWR has indicated conditional approval of the designated floodway map change. No structures may be built until a letter of map revision has been approved by FEMA.
         p.   The application for a structure shall be accompanied by drawings of the site, drawn to scale, showing property line dimensions and existing ground elevations and all changes in grade resulting from any proposed excavation or filling, and floodplain and floodway limits; sealed by a registered professional engineer, or registered land surveyor; the location and dimensions of all buildings and additions to buildings; and the elevation of the lowest floor (including basement) of all proposed buildings subject to the requirements of section 14-1-9 of this chapter.
         q.   If the proposed project involves a channel modification, the applicant shall submit the following information:
            (1)    A discussion of the purpose and need for the proposed work.
            (2)    A discussion of the feasibility of using alternative locations or methods to accomplish the purpose of the proposed work.
            (3)    An analysis of the extent and permanence of the impacts the project would have on the physical and biological conditions of the body of water affected.
            (4)    An analysis of the extent and permanence of the impacts each feasible alternative identified in subsections B1d and B1i of this section would have on the physical and biological conditions of the body of water affected.
            (5)    An analysis of the impacts of the proposed project considering cumulative effects on the physical and biological conditions of the body of water affected.
      2.   The director of engineering shall be responsible for obtaining from the applicant copies of all other local, state and federal permits and approvals that may be required for this type of activity. The community development director shall not issue the development permit unless all required federal and state permits have been obtained. A registered professional engineer, under the employ or contract of the city, shall review and approve applications reviewed under this section.
   B.   Preventing Increased Damages And A List Of Appropriate Uses: The only developments in a floodway which will be allowed are appropriate uses, which will not cause a rise in the base flood elevation, and which will not create a damaging or potentially damaging increase in flood heights or velocity or be a threat to public health and safety and welfare or impair the natural hydrologic and hydraulic functions of the floodway or channel, or permanently impair existing water quality or aquatic habitat. Construction impacts shall be minimized by appropriate mitigation methods as called for in this chapter. Only those appropriate uses listed in 17 Illinois administrative code 3708 will be allowed. Appropriate uses do not include the construction or placement of any new structures, fill, building additions, buildings on stilts, excavation or channel modifications constructed to accommodate otherwise misappropriate uses in the floodway, fencing (including landscaping or planting designed to act as a fence) and storage of materials except as specifically defined above as an appropriate use.
      1.   Appropriate Uses: The approved appropriate uses are as follows:
         a.   Flood control structures, dikes, dams and other public works or private improvements relating to the control of drainage, flooding, erosion or water quality or habitat for fish and wildlife.
         b.   Structures or facilities relating to the use of, or requiring access to, the water or shoreline, such as pumping and treatment facilities, and facilities and improvements related to recreational boating, commercial shipping and other functionally water dependent uses.
         c.   Storm and sanitary sewer outfalls.
         d.   Underground and overhead utilities.
         e.   Recreational facilities such as playing fields and trail systems including any related fencing (at least 50 percent open when viewed from any 1 direction) built parallel to the direction of flood flows and including open air pavilions. Replacement fences that do not result in greater obstructions to flood flows are permitted.
         f.   Bridges, culverts, roadways, sidewalks, railways, runways and taxiways and any modification thereto.
         g.   Parking lots and any modifications thereto (where depth of flooding at the 100-year frequency flood event will not exceed 1.0 foot) and aircraft parking aprons built at or below ground elevation.
=         h.   Designated floodway regrading, without fill, to create a positive nonerosive slope toward a watercourse.
         i.   Floodproofing activities to protect previously existing lawful structures including the construction of watertight window wells, elevating structures, or construction of floodwalls around residential, commercial or industrial principal structures where the outside toe of the floodwall shall be no more than ten feet (10') away from the exterior wall of the existing structure, and which are not considered substantial improvements to the structure.
         j.   The replacement, reconstruction, or repair of a damaged building, provided that the outside dimensions are not increased; provided, however, that if the building qualifies as substantially damaged, the building must be protected from flooding to the flood protection elevation.
         k.   Modifications to an existing building that would not increase the enclosed floor area of the building below the 100-year frequency flood elevation, and which will not block flood flows. Fireplaces, bay windows, decks, patios, and second story additions are permitted. If the modification constitutes a substantial improvement, the building must be protected to the flood protection elevation.
         l.   Elevation certificates will be required for all work within the 100-year floodplain that would require the issuance of a building permit by the city or as directed by the director of public works and engineering.
      2.   Construction Engineering And Mitigation Criteria: Within the designated floodway as identified on the designated floodway maps designated by OWR, the construction of an appropriate use will be considered permissible; provided, that the proposed project meets the following engineering and mitigation criteria and is so stated in writing with supporting plans, calculations and data by a registered professional engineer, and provided that any structure meets the protection requirements of section 14-1-9 of this chapter.
         a.   Preservation Of Flood Conveyance, So As Not To Increase Flood Stages Upstream: For appropriate uses other than bridge or culvert crossings, on stream structures or dams, all effective regulatory floodway conveyance lost due to the project will be replaced for all flood events up to and including the 100-year frequency flood. In calculating effective designated floodway conveyance, the following factors shall be taken into consideration:
            (1)    Regulatory floodway conveyance,
 
"K" = 1.486 AR 2/3
    n
 
Where "n" is Manning's roughness factor, "A" is the effective area of the cross section, and "R" is the ratio of the area to the wetted perimeter. (See "Open Channel Hydraulics", Ven Te Chow, 1959, McGraw-Hill Book Company, New York.)
            (2)    The same Manning's "n" value shall be used for both existing and proposed conditions unless a recorded maintenance agreement with a federal, state or local unit of government can assure the proposed conditions will be maintained or the land cover is changing from a vegetative to a nonvegetative land cover.
            (3)    Transition sections shall be provided and used in calculations of effective regulatory floodway conveyance. The following expansion and contraction ratios shall be used unless an applicant's engineer can prove to OWR through engineering calculation or model tests that more abrupt transitions may be used with the same efficiency:
               (A)   When water is flowing from a narrow section to a wider section, the water should be assumed to expand no faster than at a rate of one foot (1') horizontal for every four feet (4') of the flooded stream's length.
               (B)   When water is flowing from a wide section to a narrow section, the water should be assumed to contract no faster than at a rate of one foot (1') horizontal for every one foot (1') of the flooded stream's length.
               (C)   When expanding or contracting flows in a vertical direction, a minimum of one foot (1') vertical transition for every ten feet (10') of stream length shall be used.
               (D)   Transition sections shall be provided between cross sections with rapid expansions and contractions and when meeting the regulatory floodway delineation on adjacent properties.
               (E)   All cross sections used in the calculations shall be located perpendicular to flood flows.
         b.   Preservation Of Floodway Storage So As Not To Increase Downstream Flooding: Compensatory storage shall be provided for any designated floodway storage lost due to the proposed work from the volume of fill or structures placed and the impact of any related flood control projects. Compensatory storage for fill or structures shall be equal to at least one and one-tenth (1.1) times the volume of floodplain storage lost. Artificially created storage lost due to a reduction in head loss behind a bridge shall not be required to be replaced. The compensatory designated floodway storage shall be placed between the proposed normal water elevation and the proposed 100-year flood elevation. All designated floodway storage lost below the existing 10-year flood elevation shall be replaced below the proposed 10-year flood elevation and all regulatory storage lost above the existing 10-year flood elevation shall be replaced above the 10-year flood elevation and below the 100-year elevation. All such excavations shall be constructed to drain freely and openly to the watercourse. If the compensatory storage will not be placed at the location of the proposed construction, the applicant's engineer shall demonstrate to OWR through a determination of flood discharges and water surface elevations that the compensatory storage is hydraulically equivalent. Finally, there shall be no reduction in floodway surface area as a result of a floodway modification.
         c.   Preservation Of Floodway Velocities So As Not To Increase Stream Erosion Or Flood Heights: For all appropriate uses, except bridges or culverts or on stream structures, the proposed work will result in no more than a ten percent (10%) increase in velocities or stage for all flood events up to and including the 100-year frequency event. However, in the case of bridges or culverts or on stream structures built for the purpose of backing up water in the stream during normal or flood flows, velocities may be increased at the structure site if scour, erosion and sedimentation will be avoided by the use of riprap or other design measures.
Any increase in stage associated with construction in the floodway is contrary to city policy, unless the increase in stage is associated with a necessary public flood control project and there is no increase in off site flood damages.
         d.   Construction Of New Bridges Or Culvert Crossings And Roadway Approaches: The proposed structure shall not result in an increase of upstream flood stages greater than one-tenth foot (0.1') when compared to the existing vertical extensions of the channel banks such as within the design protection grade of existing levees or floodwalls or within recorded flood easements. If the proposed construction will increase upstream flood stages greater than one-tenth foot (0.1'), the developer must contact OWR, dam safety section for a dam safety permit or waiver. Any increase in stage associated with construction in the floodway is contrary to city policy, unless the increase in stage is associated with a necessary public flood control project and there is no increase in off site flood damages.
            (1)    The engineering analysis of upstream flood stages must be calculated using the flood study flows, and corresponding flood elevations for tail water conditions for the flood study specified in section 14-1-5 of this chapter. Culverts must be analyzed using the HY-8 or other hydraulic calculations approved by the director of public works and engineering for the selection of highway culverts. Bridges must be analyzed using the IDOT drainage manual.
            (2)    Lost floodway storage must be compensated for per subsection B2b of this section.
            (3)    Velocity increases must be mitigated per subsection B2c of this section.
            (4)    If the crossing is proposed over public water that is used for recreational or commercial navigation, an army corps of engineers and IDNR/OWR permit must be received.
            (5)    The hydraulic analysis for the backwater caused by the bridge showing the existing condition and proposed regulatory profile must be submitted to OWR for concurrence that a CLOMR is not required by subsection 14-1-8B of this chapter.
            (6)    All excavations for the construction of the crossing shall be designed per subsection B2h of this section.
         e.   Reconstruction Or Modification Of Existing Bridges, Culverts And Approach Roads:
            (1)    The bridge or culvert and roadway approach reconstruction or modification shall be constructed with no more than one-tenth foot (0.1') increase in backwater over the existing flood profile for all flood frequencies up to and including the 100-year event, if the existing structure is not a source of flood damage.
            (2)    If the existing bridge or culvert and roadway approach is a source of flood damage to buildings or structures in the upstream floodplain, the applicant's engineer shall evaluate the feasibility of redesigning the structure to reduce the existing backwater, taking into consideration the effects on flood stages on upstream and downstream properties.
            (3)    The determination as to whether or not the existing crossing is a source of flood damage and should be redesigned must be prepared in accordance with the IDNR/OWR 17 Illinois administrative code 3708 (floodway construction in northeastern Illinois) and submitted to the division for review and concurrence before a permit is issued.
         f.   On Stream Structures Built For The Purpose Of Backing Up Water: Any increase in upstream flood stages greater than zero feet (0.0') when compared to the existing conditions, for all flood events up to and including the 100-year frequency event shall be contained within the channel banks (or within existing vertical extensions of the channel banks) such as within the design protection grade of existing levees or floodwalls or within recorded flood easements. A permit or letter indicating a permit is not required must be obtained from OWR, dam safety section for a dam safety permit or waiver for any structure built for the purpose of backing up water in the stream during normal or flood flow. All dams and impoundment structures as defined in section 14-1-2 of this chapter shall meet the permitting requirements of 17 Illinois administrative code 3702 (construction and maintenance of dams). If the proposed activity involves a modification of the channel or floodway to accommodate an impoundment, it shall be demonstrated that:
            (1)    The impoundment is determined to be in the public interest by providing flood control, public recreation or regional stormwater detention.
            (2)    The impoundment will not prevent the migration of indigenous fish species, which require access to upstream areas as part of their life cycle, such as for spawning.
            (3)    The impoundment will not cause or contribute to degraded water quality of habitat conditions. Impoundment design should include gradual bank slopes, appropriate bank stabilization measures, and a presedimentation basin.
            (4)    A nonpoint source control plan has been implemented in the upstream watershed to control the effects of sediment runoff as well as minimize the input of nutrients, oil and grease, metals and other pollutants. If there is more than one municipality in the upstream watershed, the municipality in which the impoundment is constructed should coordinate with upstream municipalities to ensure comprehensive watershed control.
            (5)    Will require the approval of the director of engineering.
            (6)    The project otherwise complies with the requirements of this section.
         g.   Floodproofing Of Existing Habitable, Residential And Commercial Structures: If construction is required beyond the outside dimensions of the existing building, the outside perimeter of the floodproofing construction shall be placed no farther than ten feet (10') away from the outside of the building. Compensation of lost storage and conveyance will not be required for floodproofing activities.
         h.   Excavation In The Floodway: When excavation is proposed in the design of bridges and culvert openings, including the modifications to and replacement of existing bridge and culvert structures, or to compensate for lost conveyance for other appropriate uses, transition sections shall be provided for the excavation. The following expansion and contraction ratios shall be used unless an applicant's engineer can prove to OWR through engineering calculations or model tests that more abrupt transitions may be used with the same efficiency:
            (1)    When water is flowing from a narrow section to a wider section, the water should be assumed to expand no faster than at a rate of one foot (1') horizontal for every four feet (4') of the flooded stream's length;
            (2)    When water is flowing from a wide section to a narrow section, the water should be assumed to contract no faster than at a rate of one foot (1') horizontal for every one foot (1') of the flooded stream's length; and
            (3)    When expanding or contracting flows in a vertical direction, a minimum of one foot (1') vertical transition for every ten feet (10') of stream length shall be used;
            (4)    Erosion/scour protection shall be provided inland upstream and downstream of the transition sections.
         i.   Channel Modifications: If the proposed activity involves a channel modification, it shall be demonstrated that:
            (1)    There are no practicable alternatives to the activity, which would accomplish its purpose with less impact to the natural conditions of the body of water affected. Possible alternatives include levees, bank stabilization, floodproofing of existing structures, removal of structures from the floodplain, clearing the channel, high flow channel or the establishment of a streamside buffer strip or greenbelt. Channel modification is acceptable if the purpose is to restore natural conditions and improve water quality and fish and wildlife habitat.
Channel modifications are particularly sensitive activities because of their potential direct impacts on channel stability, conveyance, water quality, habitat and aesthetics. In general, watercourse modifications should be avoided unless necessary to achieve the purposes of an appropriate use, such as habitat restoration or a public flood control project. Rigorous enforcement of mitigation requirements for necessary modifications can eliminate some of the temporary and most of the permanent impacts of modification;
            (2)    Water quality, habitat and other natural functions would be significantly improved by the modification and no significant habitat area may be destroyed, or the impacts are offset by the replacement of an equivalent degree of natural resource values;
            (3)    The activity has been planned and designed and will be constructed in a way which will minimize its adverse impacts on the natural conditions of the body of water affected, consistent with the following criteria:
               (A)   The physical characteristics of the modified channel shall match as closely as possible those of the existing channel in length, cross section, slope and sinuosity. If the existing channel has been previously modified, restoration of more natural physical conditions should be incorporated into channel modification design, where practical.
               (B)   Hydraulically effective transitions shall be provided at both the upstream and downstream ends of the project, designed such that they will prevent erosion.
               (C)   Clearing of vegetation shall be limited to that which is essential for construction of the channel.
               (D)   Channel banks shall be constructed with a side slope no steeper than three to one (3:1) horizontal to vertical, wherever practicable. Natural vegetation and gradual side slopes are the preferred methods for bank stabilization. Where high velocities or sharp bends necessitate the use of alternative stabilization measures, natural rock or riprap are preferred materials. Artificial materials such as concrete, gabions, or construction rubble should be avoided unless there are no practicable alternatives.
               (E)   All disturbed areas associated with the modification shall be seeded or otherwise stabilized as soon as possible upon completion of construction. Erosion blanket or an equivalent material shall be required to stabilize disturbed channel banks prior to establishment of the vegetative cover.
               (F)   If the existing channel contains considerable bottom diversity such as deep pools, riffles and other similar features, such features shall be provided in the new channel. Spawning and nesting areas and flow characteristics compatible with fish habitat shall also be established, where appropriate.
               (G)   A sediment basin and other erosion protection devices shall be installed at the downstream end of the modification to reduce sedimentation and degradation of downstream water quality.
               (H)   New or relocated channels should be built in the dry and all items of construction, including vegetation, should be completed prior to diversion of water into the new channel.
               (I)   There shall be no increases in stage or velocity as the channel enters or leaves the project site for any frequency flood unless necessitated by a public flood control project or unless such an increase is justified as part of a habitat improvement or erosion control project.
               (J)   Unless the modification is for a public flood control project, there shall be no reduction in the volume of floodwater storage outside the floodway as a result of the modification.
            (4)    The project otherwise complies with the requirements of this section.
         j.   Seeding And Stabilization Plan: For all activities located in a floodway, a seeding and stabilization plan shall be submitted by the applicant.
         k.   Soil Erosion And Sedimentation Measures: For all activities in the floodway, including grading, filling and excavation, in which there is potential for erosion of exposed soil, soil erosion and sedimentation control measures shall be employed consistent with the following criteria:
            (1)    The construction area shall be minimized to preserve the maximum vegetation possible. Construction shall be scheduled to minimize the time soil is exposed and unprotected. In no case shall the existing natural vegetation be destroyed, removed or disturbed more than fifteen (15) days prior to the initiation of improvements.
            (2)    Temporary and/or permanent soil stabilization shall be applied to denuded areas as soon as possible. As a minimum, soil stabilization shall be provided within fifteen (15) days after final grade is reached on any portion of the site, and within fifteen (15) days to denuded areas, which may not be at final grade but will remain undisturbed for longer than sixty (60) days.
A schedule outlining the method and employment of sediment and erosion protection methods prior to, during and after all construction, must be submitted to the director of engineering.
            (3)    Sedimentation control measures shall be installed before any significant grading or filling is initiated on the site to prevent the movement of eroded sediments off site or into the channel. Potential sediment control devices include filter fences, straw bale fences, check dams, diversion ditches and sediment basins.
            (4)    A vegetated buffer strip of at least twenty five feet (25') in width shall be preserved and/or reestablished, where possible, along existing channels (subsection B2p of this section). Construction vehicle use of channels shall be minimized. Temporary stream crossings shall be constructed, where necessary, to minimize erosion. Necessary construction in or along channels shall be restabilized immediately.
            (5)    Soil erosion and sedimentation control measures shall be designed and implemented consistent with "Procedures And Standards For Urban Soil Erosion And Sedimentation Control In Illinois" (1988) also known as the "Green Book" and "Standards And Specifications For Soil Erosion And Sediment Control" (IEPA, 1987).
         l.   Public Flood Control Projects: For public flood control projects, the permitting requirements of this section will be considered met if the applicant can demonstrate to OWR through hydraulic and hydrologic calculations that the proposed project will not singularly or cumulatively result in increased flood heights outside the project right of way or easements for all flood events up to and including the 100-year frequency event.
         m.   General Criteria For Analysis Of Flood Elevations:
            (1)    The flood profiles, flows and floodway data in the regulatory floodway study, referenced in section 14-1-5 of this chapter must be used for analysis of the base conditions. If the study data appears to be in error or conditions have changed, OWR shall be contacted for approval and concurrence on the appropriate base conditions data to use.
            (2)    If the 100-year designated floodway elevation at the site of the proposed construction is affected by backwater from a downstream receiving stream with a larger drainage area, the proposed construction shall be shown to meet the requirements of this section for the 100-year frequency flood elevations of the designated floodway conditions and conditions with the receiving stream at normal water elevations.
            (3)    If the applicant learns from OWR, local governments or a private owner that a downstream restrictive bridge or culvert is scheduled to be removed, reconstructed, modified, or a regional flood control project is scheduled to be built, removed, constructed or modified within the next five (5) years, the proposed construction shall be analyzed and shown to meet the requirements of this section for both the existing conditions and the expected flood profile conditions when the bridge, culvert or flood control project is built.
         n.   Conditional Letter Of Map Revision: If the appropriate use would result in a change in the designated floodway location or the 100-year frequency flood elevation, the applicant shall submit to OWR and to FEMA all the information, calculations and documents necessary to be issued a conditional designated floodway map revision and receive from OWR a conditional approval of the regulatory floodway change before a permit is issued. However, the final designated floodway map will not be changed by OWR until as built plans or record drawings are submitted and accepted by FEMA and OWR. In the case of nongovernment projects, the municipality in incorporated areas and the county in unincorporated areas shall concur with the proposed conditional designated floodway map revision before OWR approval can be given. No filling, grading, dredging or excavating shall take place until a final letter of map revision (LOMR) is issued by FEMA and OWR.
         o.   Professional Engineer's Supervision: All engineering analyses shall be performed by or under the supervision of a registered professional engineer.
         p.   Protection From Construction: For all activities in the floodway involving construction within twenty five feet (25') of the channel, the following criteria shall be met:
            (1)    A natural vegetation buffer strip shall be preserved within at least twenty five feet (25') of the ordinary high water mark of the channel.
            (2)    Where it is impossible to protect this buffer strip during the construction of an appropriate use, a vegetated buffer strip shall be established upon completion of construction.
            (3)    The use of native riparian vegetation is preferred in the buffer strip. Access through this buffer strip shall be provided, when necessary, for stream maintenance purposes.
After receipt of conditional approval of the designated floodway change and issuance of a permit and a conditional letter of map revision, construction as necessary to change the designated floodway may proceed but no buildings or structures or other construction that is not an appropriate use may be placed in that area until the designated floodway map is changed and a final letter of map revision is received. The designated floodway map will be revised upon acceptance and concurrence by OWR and FEMA of the as built plans.
      3.   State Review: For those projects listed below located in a designated floodway, the following criteria shall be submitted to OWR for their review and concurrence prior to the issuance of a permit:
         a.   OWR will review an engineer's analysis of the flood profile due to a proposed bridge pursuant to subsection B2d of this section.
         b.   OWR will review an engineer's determination that an existing bridge or culvert crossing is not a source of flood damage and the analysis indicating the proposed flood profile, pursuant to subsection B2e of this section.
         c.   The OWR will review alternative transition sections and hydraulically equivalent storage pursuant to subsections B2a, B2b and B2h of this section.
         d.   The OWR will review and approve, prior to the start of construction, any department projects, dams (as defined in this chapter) and all other state, federal or local units of government projects, including projects of the municipality or county.
      4.   Other Permits: In addition to the other requirements of this chapter, a development permit for a site located in a floodway shall not be issued unless the applicant first obtains a permit or written documentation that a permit is not required from OWR and the army corps of engineers, issued pursuant to 615 Illinois Compiled Statutes 5/5. No permit from OWR shall be required if the division has delegated this responsibility to the city.
      5.   Dam Safety Permits: Any work involving the construction, modification or removal of a "dam" as defined in section 14-1-2 of this chapter per 17 Illinois administrative code 3702 (rules for construction of dams) shall obtain an Illinois division of water resources dam safety permit prior to the start of construction of a dam. If the director of engineering finds a dam that does not have an OWR permit, the director of engineering shall immediately notify the dam safety section of the division of water resources. If the director of engineering finds a dam, which is believed to be in an unsafe condition, the director of engineering shall immediately notify the owner of the dam, OWR, dam safety section in Springfield and the Illinois emergency management agency (IEMA).
      6.   Activities That Do Not Require A Registered Professional Engineer's Review: The following activities may be permitted without a registered professional engineer's review. Such activities shall still meet the other requirements of this chapter, including the mitigation requirements.
         a.   Underground and overhead utilities that:
            (1)    Do not result in any increase in existing ground elevations, or
            (2)    Do not require the placement of aboveground structures in the floodway, or
            (3)    In the case of underground stream crossings, the top of the pipe or encasement is buried a minimum of three feet (3') below the existing streambed, and
            (4)    In the case of overhead utilities, supporting towers are placed in the watercourse and are designed in such a fashion as not to catch debris.
         b.   Storm and combined sewer outfalls that:
            (1)    Do not extend riverward or lakeward of the existing adjacent natural bank slope, and
            (2)    Do not result in an increase in ground elevation, and
            (3)    Are designed so as not to cause stream erosion at the outfall location.
         c.   Construction of sidewalks, athletic fields (excluding fences), properly anchored playground equipment and patios at grade.
         d.   Construction of shoreline and stream bank protection that:
            (1)    Does not exceed one thousand feet (1,000') in length.
            (2)    Materials are not placed higher than the existing top of bank.
            (3)    Materials are placed so as not to reduce the cross sectional area of the stream channel or bank of the lake.
            (4)    Vegetative stabilization and gradual side slopes are the preferred mitigation methods for existing erosion problems. Where high channel velocities, sharp bends or wave action necessitate the use of alternative stabilization measures, natural rock or riprap are preferred materials. Artificial materials such as concrete, construction rubble and gabions should be avoided unless there are no practicable alternatives.
            (5)    Use of artificial shoreline and stream bank materials for the convenience of site design for private developments is not supported. Construction activities involving one thousand feet (1,000') of shoreline or stream bank are not minor and should be subject to the review of a registered professional engineer.
         e.   Temporary stream crossings in which:
            (1)    The approach roads will be five-tenths foot (0.5') or less above natural grade.
            (2)    The crossing will allow stream flow to pass without backing up the water above the stream bank vegetation line or above any drainage tile or outfall invert.
            (3)    The top of the roadway fill in the channel will be at least two feet (2') below the top of the lowest bank. Any fill in the channel shall be nonerosive material, such as riprap or gravel.
            (4)    All disturbed stream banks will be seeded or otherwise stabilized as soon as possible upon installation and again upon removal of construction.
            (5)    The access road and temporary crossing will be removed within one year after authorization. (Ord. M-15-16, 6-6-2016)