§ 9-221 BUILDING DEMOLITION; COMPLETION.
   All demolition work must be completed within 90 days from the date of the demolition permit. To be considered complete, all materials from the demolished structure, including, but not limited to, foundation and concrete slabs, must be removed from the premises. Upon completion of the demolition work, the applicant shall clean the premises of all remaining debris, fill in the excavation and grade the area with top soil or other material approved by the municipality.
(Ord. 968, passed 10-4-2022)