Prior to the granting of Final Plat approval, the subdivider shall have installed or shall have furnished adequate bond, as provided in Section 1181.13 hereof, for the ultimate installation of the following:
(a) The subdivider shall provide a complete water distribution system, including a connection for each lot and appropriately spaced fire hydrants. Such water system shall conform to all applicable requirements of the Village of Delta.
(b) Each lot must be served by individual water line connections, except in the case of duplexes, which may be served with an approved wye tap, provided that each unit has an individual shut-off valve. Each dwelling unit, whether single family or multifamily, must have an individual meter easily accessible.
(c) All water line connections (tap-ins) will be made by the Village. The subdivider will provide all excavation, backfill, and compaction; and all excavations shall be safe to enter as determined by Village employees. Backfill material in roadways, driveways, and sidewalks shall meet appropriate ODOT specifications. The Village Administrator must be notified two (2) business days in advance of the work to be performed.
(d) All water service connections shall be of copper pipe, sufficiently sized to provide adequate water service.
(e) Where a public water supply is used, water supply lines shall be installed within the public road right-of-way, unless exceptional circumstances warrant their location elsewhere. Regardless of the location of the water supply lines, fire hydrants must be located within the road right-of-way.
(Ord. 95-35. Passed 11-20-95.)