Prior to the granting of Final Plat approval, the subdivider shall have installed or shall have furnished adequate bond, as provided in Section 1181.13 hereof, for the ultimate installation of the following:
(a) All lots shall be graded so that all storm water will drain therefrom. Such grading shall not cause ponding on properties adjacent to the plat, add areas of storm water runoff nor provide points of extreme concentration on them not existing prior to the proposed development.
(b) The basement or other lowest floor elevation shall be at a minimum elevation of one (1) foot above the estimated high water level of any area affected or likely to be affected by the flooding of public watercourses. Such elevations shall be a matter of public record and recited on the final plat. Compliance with this section shall be a condition of obtaining building and occupancy permits.
(Ord. 95-35. Passed 11-20-95.)