§ 11.01.250.080 CONDITIONAL USE PERMIT REQUIREMENTS.
   (A)   If the project is determined to involve the displacement/excavation of more than five cubic yards of earthen material or import of more than five cubic yards of fill within the Overlay District (unless waived by the City Planner or exempt under § 11.01.250.040), the applicant shall apply for a conditional use permit (see §§ 11.01.120.010 through 11.01.120.090).
   (B)   All conditional use permit requests within the Overlay District shall be reviewed through the conditional use permit procedure as described in §§ 11.01.120.010 through 11.01.120.090.
   (C)   Conditional use permit review under this chapter is limited to that required for ground disturbance activities and water features that are part of the Superfund remedy. Reviews for land uses listed in the underlying zoning district for which a conditional use permit is required may be reviewed at the same time as a conditional use permit under this chapter, but the focus of the conditional use permit process under this chapter is to provide review and assure compliance with the Superfund remedy for the site.
(Prior Code, § 11.01.250.080) (Ord. 171, passed 9-17-2018; Ord. 2021-15, passed 12-20-2021)