§ 151.11 COMPLETION OF WORK.
   Work will be considered complete when all exposed soil areas have undergone final stabilization and have permanent cover, as defined in § 151.05 of this chapter, is constructed to finish grade, is in conformance with all permit conditions of approval to the satisfaction of the city, and has passed a final inspection. The applicant or representative shall notify the issuing authority when the land disturbing operations are ready for final inspection. Final approval shall not be given until all work, including installation of all drainage facilities and their protective devices, and all erosion control measures, have been completed and final stabilization has occurred in accordance with this chapter.
(Ord. 2005-04, passed 3-22-2005; Ord. 2020-09, passed 4-14-2020)