1281.04 SITE AND BUILDING PLACEMENT.
   (a)   Building Placement.
      (1)   Minimum lot width: sixty (60) feet.
      (2)   Minimum lot size: none.
      (3)   Front yard setback: twenty-five (25) feet or the existing building setback. If it is less than twenty-five (25) feet and the building is to remain.
      (4)   Side yard: fifteen (15) feet each side, except that street side yards shall be twenty-five (25) feet. The Planning Commission may require the installation of a solid, six (6) foot tall approved fence that provides for high quality and low maintenance.
      (5)   Parking requirements. Off-street parking shall not be the dominant feature of the site. Off-street parking and circulation drives are not permitted within ten (10) feet of the road right-of-way or within the front yard setback.
 
   (b)   Lot Requirements.
      (1)   Maximum lot coverage: forty percent (40%).
      (2)   There is no minimum lot size.
      (3)   Lots shall be a minimum of sixty (60) feet in width.
      (4)   There is no minimum lot depth except that no lot depth to width ratio shall exceed 4:1.
      (5)   All properties are required to provide pedestrian access and accommodation as follows:
         A.   A five (5) foot wide public walk along the street with brick soldier course.
         B.   A five (5) foot wide walk connection from the public walk to the development is required.
      (6)   Rear yard setbacks: No building shall be located closer than twenty-five (25) feet to the rear property line. For nonresidential developments, the following provisions also apply:
         A.   A minimum five (5) foot landscaped buffer shall be installed between any pavement and adjacent use.
         B.   The Planning Commission may require the installation of a solid, six (6) foot tall approved fence that provides for high quality and low maintenance.
   (c)   Development Incentives. Development may increase their required overall lot coverage by ten percent (10%) if a structural element is added for visual interest. This includes arbors, trellises, gateways, and gazebos. The structure, its placement and form, must be approved as part of the original development.