§ 152.34 WATERSHED PROTECTION OCCUPANCY PERMIT.
   (A)   The Watershed Administrator shall issue a Watershed Protection Occupancy Permit certifying that all requirements of this chapter have been met prior to the occupancy or use of a building hereafter erected, altered or moved and/or prior to the change of use of any building or land.
   (B)   A Watershed Protection Occupancy Permit, either for the whole or part, of a building, shall be applied for coincident with the application for a Watershed Protection Permit and shall be issued or denied within ten days after the erection or structural alterations of the building.
   (C)   When only a change in use of land or existing building occurs, the Watershed Administrator shall issue a Watershed Protection Occupancy Permit certifying that all requirements of this chapter have been met coincident with the Watershed Protection Permit.
   (D)   If the Watershed Protection Occupancy Permit is denied, the Watershed Administrator shall notify the applicant in writing stating the reasons for denial.
   (E)   No building or structure which has been erected, moved, or structurally altered may be occupied until the Watershed Administrator has approved and issued a Watershed Protection Occupancy Permit.