§ 154.04 ISSUANCE OR DENIAL OF PERMIT.
   Upon completion of the conditions of § 154.03, the Building Inspector shall, within 60 days, either issue a permit authorizing the construction of a well in accordance with the approved engineering plans or deny the permit. Upon denial of the permit, the person aggrieved shall have 10 days in which to request a hearing before the Board of Commissioners by service of written notice of appeal from the decision of the Building Inspector upon the Board of Commissioners. Within 30 days after the service, the Board of Commissioners shall hold a hearing, at a time and place designated by the Board of Commissioners, at which time the Board of Commissioners may uphold the decision of the Building Inspector, direct the issuance of a permit by the Building Inspector, or direct the issuance of a conditional permit by the Building Inspector, which may require compliance with the reasonable conditions as may not be contrary to the intent and purposes of this chapter.
(Prior Code, § 154.04) (Ord. passed 4-2-1973)