19-3.10   Time Limits of Grading Operations.
   a.   The permittee shall fully perform and complete all of the work required to be done pursuant to the permit within the time limit specified therein or, if no time is so specified, within one hundred eighty (180) days after the date of issuance of the permit.
   b.   If the work is not completed within the specified time, a request for an extension of time setting forth the reasons for the requested extension shall be presented in writing to the Town Engineer. The Town Engineer may grant additional time for the work.
   c.   If all the permit work required is not completed within the time limit specified in paragraph a. above, no further grading shall be done without renewing the permit. A written request for renewal shall be submitted to the Town Engineer. A new application may be required considering the time between the expiration date and the renewal request, changes in Town regulations or subsequent development in the immediate area. Plans must be revised and rechecked.
(Ord. #89-22, §92-8.19)