5-3-13: PROJECT REVIEW FOR DEVELOPMENT:
   A.   When determined necessary by the Planning Administrator, a project review meeting shall be required prior to processing building permit or site disturbance permit applications in the commercial zone. The project proponent must submit a complete description of the project, including all information on the forms provided by the city. Staff may request additional information prior to sending the request to the project review team.
   B.   The project review team includes the project proponent, and city representatives from planning, building and engineering. It may include fire department representatives, health district representatives and representatives from the Dalton Gardens Water Association, Dalton irrigation district, and the City of Coeur d’Alene.
   C.   At the project review meeting, the project review team will determine the types of approvals that will be necessary and provide an estimate of required fees for the project. The project review team may impose conditions on the project to mitigate impacts.
   D.   A site inspection may be deemed necessary by the City.
   E.   The burden of proof to provide correct information lies with the project proponent and property owner. (Ord. 221, 7-12-2012; amd. Ord. 264, 3-5-2020; Ord. 272, 9-14-2021)