Design review fees. The rates for reviewing engineering plans for the construction of water and wastewater facilities for the purpose of development or redevelopment are as follows:
(1) $1,050 for design review of engineering plans requiring more than 100 feet of construction of water and wastewater mains, excluding the footage of building service connections.
(2) $300 for design review of engineering plans requiring 100 feet or less of construction of water and wastewater mains, excluding the footage of building service connections.
(3) $300 for each additional design review of engineering plans for:
(A) every design review submission in excess of three engineering design reviews, which submission was not required as a result of a review error by the city; and
(B) each design revision submitted after construction has commenced, which submission was not required as a result of a review error by the city. (Ord. Nos. 19201; 20215; 22208; 23289; 27355)