§ 17.595.035 CHANGES TO AN APPROVED PROJECT.
   An approved development or new land use shall be established only as specified by the approved land use permit, and subject to any conditions of approval. An applicant may request, in writing, to amend the approved permit, and shall furnish appropriate supporting materials and an explanation of the reasons for the request.
   A.   Minor changes may be approved, modified, or denied by the Director. Major changes shall be approved, modified or denied by the original review authority.
   B.   The Director shall determine whether a proposed change is major or minor. The determination that the change is major depends on whether the proposal may result in:
      1.   Significant impacts to the surrounding neighborhood.
      2.   Significant environmental impacts.
      3.   A change to the approved use or a significant change to project design.
      4.   A change to the basis on which the environmental determination for the project was made.
      5.   A change to the basis upon which the review authority made the findings for approval of the project.
   A major change request shall be processed in the same manner as the original permit or entitlement.
(Ord. No. 2005-007 § 1 (part))