A. The Grantee shall comply with the requirements of the system construction schedule contained in the Franchise Agreement.
B. The Grantee shall provide a detailed construction plan indicating progress schedule, area construction maps, test plan, and projected dates for offering service. In addition, the Grantee shall update this information on a monthly basis, by submitting a copy of its normal internal progress reports, showing specifically whether schedules are being met and the reasons for any delay.
('65 Code, § 35B-6(d)) (Ord. No. 87-021 § 1; Ord. No. 2001-009 § 1)