§ 153.050 PERMIT REQUIRED.
   A permit must be obtained from the Zoning Administrator to verify a development meets the standards outlined in this chapter prior to conducting the following activities:
   (A)   The erection, addition, modification, rehabilitation, or alteration of any building, structure, or portion thereof. Normal maintenance and repair also requires a permit if such work, separately or in conjunction with other planned work, constitutes a substantial improvement as defined in § 153.007;
   (B)   The use or change of use of a building, structure, or land;
   (C)   The construction of a dam, on-site septic system, or fence, although a permit is not required for a farm fence as defined in § 153.007;
   (D)   The change or extension of a nonconforming use;
   (E)   The repair of a structure that has been damaged by flood, fire, tornado, or any other source;
   (F)   The placement of fill, excavation of materials, or the storage of materials or equipment within the floodplain;
   (G)   Relocation or alteration of a watercourse, including new or replacement culverts and bridges, unless a public waters work permit has been applied for; or
   (H)   Any other type of development as defined in § 153.007.
(Ord. 2017-03, passed 7-24-2017)