8-1A-7: EXTENSION OF SEWER MAINS:
   (A)   The board of trustees shall first determine if an extension of a sewer main is economically feasible based on the estimated cost of the extension and the number of existing potential users that will be served by the extension. If the extension is economically feasible then the village may install and pay the cost of the extension at the discretion of the board of trustees. If the village elects not to pay the cost of extending the sewer main then the person or persons desiring sewer service shall install the extension at their own personal expense upon written consent by the board of trustees. The village shall not pay for any extensions to an undeveloped area such as a subdivision being developed.
   (B)   When a sewer extension is installed by someone other than the village the following conditions must be satisfied:
      1.   The village must approve all plans and specifications for any extensions. The cost to the village of reviewing and approving the plans and specifications shall be paid by the person submitting the documents.
      2.   Before any extensions are installed, the plans and specifications must be reviewed and approved by the state of Illinois, environmental protection agency.
      3.   Ownership, rights of way, and title must be conveyed to the village for all extensions installed by anyone other than the village. The village will maintain the mains thereafter.
      4.   No extension will be permitted if, in the opinion of the board of trustees, the system does not have the necessary capacity to serve the proposed extension. (Ord. 499, 8-22-1985)