§ 53.15 RELOCATION OR REMOVAL.
   (A)   The city at all times retains the right to order the modification, relocation or removal of a wireless support structure within the city right-of-way for public improvement projects.
   (B)   Any modification, relocation, or removal shall be completed with 120 days of written notice by the city unless exigencies dictate a shorter period for removal or relocation.
   (C)   Relocation or removal shall require a permit.
   (D)   The permittee shall be entitled, at permittees election, to either a pro-rata refund of fees paid for the original permit or to a new permit, without additional fee, at a location as close to the original location as permissible under this chapter.
   (E)   In the event said facility is not modified, relocated, or removed within said period, the city may cause the same to be done at the sole cost and expense of permittee.
   (F)   Structures may be modified, relocated, or removed without notice to permittee by city for the immediate public safety and welfare, provided notice is provided to the permittee within three working days following modification, relocation, or removal.
(Ord. 2019-02-01, passed 3-14-19)