§ 91.52 INSTALLATION, RELOCATION, OR DISCONTINUATION OF FACILITIES.
   (A)   Provisions apply unless direct conflict exists. The provisions of this section shall apply unless they directly conflict with a tariff, state or Federal law, or the provisions of the applicant's franchise agreement with the city. This section shall not be interpreted to impair the ability of a registrant to perform work not requiring a permit unless a public safety concern would arise if such work were to be performed.
   (B)   General application. Upon the written notice of and at the direction of the Director, a registrant shall relocate or remove facilities, or rearrange aerial facilities, if required by a tariff, state or Federal law, a franchise agreement with the city, or the provisions of this subchapter.
   (C)   Coordination. To the extent reasonably possible, registrants shall coordinate the installation, relocation, and removal of their facilities with each other in order to avoid issues with respect to the location of facilities within the right-of-way.
   (D)   Procedure. The Director shall notify the applicant if the Director determines that a facility may not be installed as requested by the applicant. Upon determining that a facility may not be installed as requested, the Director shall provide written notice to the applicant as early as practicable and in conformity with any specific applicable notice requirement. The notice shall contain a description of the area affected as well as the reason for the Director's determination. The Director may issue a permit that is contingent upon certain condition(s) being fulfilled with respect to the criteria contained below.
   (E)   Reservation of rights. Notwithstanding any other provision in this subchapter, the city specifically reserves the right to order the removal or relocation of any facility installed after the effective date of this chapter, at no cost to the city, for which the appropriate permit was not obtained.
   (F)   Preclusion on cutting newly paved surfaces.
      (1)   If any street is designated for resurfacing or reconstruction by the city on the list maintained pursuant to this subchapter, the registrant shall make any extensions, changes, or installations of or to its facilities ahead of such activity. The registrant shall notify the Director no less than forty-five (45) days prior to the city's anticipated bid date of its desire to perform such extensions, changes, or installations, and may be allowed up to ninety (90) additional days to complete the work.
      (2)   If any street is about to be constructed, reconstructed, widened, altered, or paved by the city, the Director shall provide notice to registrants, and the registrant shall make any extensions, changes, or installations of or to its facilities ahead of such activity. Depending on the amount of such extensions, changes, or installations to be performed, the registrant may be allowed up to one hundred twenty (120) days to complete the work, which the Director may extend for good cause. It is expected that the registrant shall not disturb the city's improvements within the following two (2) year period, so as to minimize the premature degradation of the right-of-way caused by multiple alterations and surface cuts. Upon a registrant's showing of undue hardship or emergency, the Director may grant permission for limited disturbment of the newly paved surface within the two (2) year period. Registrant shall in those instances comply with all other relevant provisions of this chapter pertaining to restoration of the right-of-way.
   (G)   Relocation.
      (1)   Upon providing reasonable advanced written notice to the registrant or other responsible party, the Director may order the relocation or rearrangement of any facility, in his or her reasonable discretion and in good faith, if any of the following arise with respect to that facility:
         (a)   The relocation or rearrangement is necessary for the purpose of public safety.
         (b)   The relocation or rearrangement is required by a tariff, state or Federal law, or a franchise agreement with the city.
         (c)   The relocation or rearrangement is necessary to assist in the installation of facilities by another registrant or permittee.
         (d)   The relocation or rearrangement is necessary as a result of the city adopting a planned public project or policy requiring that facilities be relocated.
         (e)   So as to conform to the established grade or line of a right-of-way or so as not to interfere with public improvements whenever the city shall grade, regrade, construct, reconstruct, widen, or alter any right-of-way, or construct, reconstruct, repair, maintain or alter a public improvement, including, but not limited to, storm sewers, or street lights therein.
      (2)   The city shall coordinate the new location with the registrant or permittee as part of the permitting process.
      (3)   Relocation underground. If, as a result of a planned public project, a registrant is required to relocate facilities that were previously and lawfully located above-ground, and the city requests, as part of the relocation, that the facilities be relocated to underground, the city shall bear the cost for the difference in cost between an aerial and underground facility of the same type, unless an agreement to the contrary is otherwise entered into by the appropriate parties.
      (4)   Relocation for public safety reasons. If the basis for the city ordering the relocation of a facility is a public safety concern, the registrant shall relocate the facility at no cost to the city.
      (5)   Relocations to assist in the placement of other facilities. If a registrant is required to relocate facilities to assist in the installation of facilities by another registrant or permittee, the party seeking to install the facilities shall bear the costs of said relocation, unless an agreement to the contrary is otherwise entered into by the appropriate parties.
      (6)   Relocations where the cost is borne by the city. Notwithstanding any language in this subchapter to the contrary, unless an agreement to the contrary is otherwise entered into by the appropriate parties, the cost of the following types of relocations shall be borne by the city:
         (a)   The relocation is the result of the city adopting a plan or policy requiring that facilities be placed underground in that location, if, at the time the facility was installed, such a plan was not in place;
         (b)   The location in which the facility is currently sited was not a part of the right-of-way or was not otherwise owned or controlled by the city at the time the facility was installed;
         (c)   The city has previously ordered that the facility be relocated to comply with a public improvement project, the registrant or party has substantially complied with such order, and the city then orders the registrant or party to relocate that facility to a different area as part of the same project; or
         (d)   The city orders the relocation of a facility to accommodate a public improvement project, and the construction of such project is subsequently terminated by the city.
   (H)   Discontinuance of use.
      (1)   Any party discontinuing use of a facility shall notify the Director in writing of such discontinued use within thirty (30) days. Said notice shall describe the facilities for which the use is to be discontinued and include a statement as to whether the registrant intends to leave the facilities in place for potential future use, remove the facilities, or abandon the facilities in place. The registrant shall remain responsible for the maintenance, repair, and condition of discontinued facilities at all times.
      (2)   The Director may order that the responsible party remove, replace, or repair any discontinued facility which significantly interferes with the city's maintenance of the right-of-way.
(Ord. 2018-11-01, passed 12-13-18)