§ 53.041 SUPERVISION AND INSPECTIONS.
   (A)   Tap-in supervision and testing. The applicant for the building sewer permit shall notify the city when the building sewer is ready for inspection and connection to the public sewer. The connection shall be made under the supervision of the Superintendent or his or her representative. At any time after the installation of the building sewer, the city may test the building sewer for violation of this chapter.
(Prior Code, § 38-4-33)
   (B)   Inspection.
      (1)   After the building sewer has been constructed in the trench but before the sewer is backfilled, the applicant for the building sewer permit shall notify the Superintendent that the building sewer is ready for inspection.
      (2)   If the sewer has been constructed properly, permission will be given to backfill the trench.
      (3)   If the sewer construction is found to be unsuitable, the permit applicant will correct the installation to meet city’s requirements.
(Prior Code, § 38-4-34)