(A) After receiving the Planning Commission recommendation on an application for a compliance permit, the Council may:
(1) Request the applicant to submit further information;
(2) Set a hearing date at the next regular meeting of the Council; or
(3) Make a final decision on the application.
(B) The Council shall make its final decision after receipt of the Planning Commission recommendation, and after the public hearing if one has been held, and after any requested additional information has been submitted. In making a final decision, the Council shall:
(1) Approve the application and issue a permit, with or without conditions; or
(2) Reject the application, filing its reasons for doing so, in writing, within five days after the decision is made.
(C) In no case shall a decision be delayed more than 30 days after receipt of the Planning Commission recommendation, after the public hearing or after the receipt of additional information requested, whichever is later.
(Ord. 294, passed 3-25-2014)