§ 151.03 BUILDING PERMIT FEES.
   (A)   Schedule A has been incorporated in the table below.
Total Valuation
Permit Fee
Total Valuation
Permit Fee
1 to 1,000
$15
1,001 to 2,000
$15
2,001 to 5,000
$25
5,001 to 7,500
$30
7,501 to 10,000
$35
10,001 to 15,000
$50
15,001 to 20,000
$55
20,001 to 50,000
$65
50,001 to 75,000
$75
75,001 to 100,000
$100
100,001 to 150,000
$250
150,001 to 200,000
$400
200,000 to 250,000
$450
250,000 to 300,000
$500
300,00 to 350,000
$550
350,000 to 400,000
$650
400,00 to 450,000
$700
450,000 to 500,000
$800
500,000 to 550,000
$850
550,000 to +600,000
$900
 
   (B)   It is the responsibility of the property owner to see that a building permit is obtained.
   (C)   It is the responsibility of the person doing the work to verify that a permit has been obtained and to contact the Building Inspector for inspections at the appropriate time.
   (D)   No permit is required for carpet, paint and similar finish work, driveways and sidewalks (except driveways and sidewalks installed parallel to the street for public use or on town property will require a permit).
(Ord. 294, passed 3-25-2014)