(A) The applicant shall be responsible for providing record drawings of all stormwater BMPs included in the approved SWM Site Plan. The record drawing and an explanation of any discrepancies with the approved SWM Site Plan shall be submitted to the city as a prerequisite for the release of the guarantee or issuance of an occupancy permit.
(B) The record drawing shall include a certification of completion signed by a Qualified Professional verifying that all permanent stormwater BMPs have been constructed according to the approved SWM Site Plan and Report.
(1) Drawings shall show all approved revisions and elevations and inverts to all manholes, inlets, pipes and stormwater control facilities.
(2) Submission shall include a comparison of the constructed stage-storage (volume vs. elevation) of all above-ground and below-ground stormwater storage facilities to the approved design.
(C) After receipt of the Record Drawing and certification of completion by the city, the city may conduct a final inspection.