§ 54.05 SUBMITTALS, REVIEW AND APPROVAL.
   (A)   A technical review and comment form stating that the plan is adequate and an improvement location permit shall be obtained prior to the initiation of any land disturbing activities.
   (B)   A complete storm water pollution prevention plan and erosion and sediment control plan (as described in the Connersville Drainage Standards Manual and in accordance with Rule 5) shall be submitted in triplicate to the Fayette County Area Planning Commission. One copy will be forwarded to the Connersville Department of Storm Water Management and one copy to the Fayette County SECD for review. If the Fayette County SWCD would like to incorporate review comments, a technical review and comment form shall be forwarded to the Connersville Department of Storm Water Management within 28 days of the date of plan submittal.
   (C)   At the time of submittal, the date and time will be recorded.
   (D)   Each application shall bear the name(s) and address(es) of the owner or developer of the project site, and of any consulting firm retained by the applicant together with the name of the applicant's principal contact at such firm and shall be accompanied by a filing fee, defined in the Connersville Drainage Standards Manual.
   (E)   (1)   Each application shall include a statement that any land clearing, construction, or development involving the movement of earth shall be in accordance with the storm water pollution prevention plan and that a certified contractor shall be on the project site on all days when construction or grading activity takes place.
      (2)   The Connersville Department of Storm Water Management will review each application for a Rule 5 permit to determine its conformance with the provisions of this regulation. Within 28 days after receiving an application, the Connersville Department of Storm Water Management shall, in writing:
         (a)   Approve the erosion and sediment control plan and SWPP and provide a technical review and comment form stating that the plan is adequate and issue an improvement location permit.
         (b)   Approve the erosion and sediment control plan and SWPP subject to such reasonable conditions as may be necessary to secure substantially the objectives of this regulation, and issue the technical review and comment form stating that the plan is adequate; or
         (c)   Provide a technical review and comment form stating that the plan is deficient and indicating the reason(s) and procedure for submitting a revised application and/or submission.
   (F)   Failure of the Connersville Department of Storm Water Management or the Fayette County Area Planning Commission to act on an original or revised application within 28 days of receipt shall authorize the applicant to proceed in accordance with the plans as filed unless such time is extended by agreement between the applicant and the Fayette County Area Planning Commission. Pending preparation and approval of a revised plan, development activities shall be allowed to proceed in accordance with conditions established by the Fayette County Area Planning Commission.
   (G)   The sufficiency of the construction plans shall be based upon Rule 5 regulations and the criteria described in the current Connersville Drainage Standards Manual.
   (H)   After receiving a technical review and comment form stating that the plan is adequate, if revisions to the construction plans require a change in measures appropriate to control the quality or quantity of storm water runoff, then revised plans must be submitted to Fayette County Area Planning Commission.
   (I)   The applicant will be required to file with the City of Connersville faithful performance bond, letter of credit, or other improvement security in an amount deemed sufficient by the City of Connersville to cover all costs of improvements, landscaping maintenance of improvements for such period as specified by the City of Connersville, and engineering and inspection costs to cover the cost of failure to repair of improvements installed on the project site.
   (J)   (1)   After receiving a technical review and comment form stating that the plan is adequate from Fayette County Area Planning Commission, and within 48 hours of the start of construction, the following shall be submitted to the Indiana Department of Environmental Management and Fayette County SWCD:
         (a)   Notice of intent form (required by 327 IAC 15-5);
         (b)   A copy of the technical review and comment form stating that the plan is adequate; and
         (c)   Proof of publication required by 327 IAC 15-5-5(9).
      (2)   A copy of the NOI must also be submitted to Connersville Department of Storm Water Management.
   (K)   The project site owner must submit a notice of termination (NOT) letter to IDEM and transmit a copy of the NOT letter to the Fayette County Area Planning Commission and Connersville Department of Storm Water Management when all land disturbing activities have been completed, the entire project site has been stabilized and all temporary erosion and sediment control measures have been removed.
(Ord. 4533, passed 10-18-04)