§ 52.110 RATES.
   (A)   Effective the January 1, 2009 billing cycle, which is for the December 2018 meter readings, rates for sanitary sewer services shall be:
      (1)   Minimum charge for 0 to 1,000 gallons per EDU: $37; and
      (2)   Charge for each 100 gallons thereafter: $0.80.
   (B)   (1)   A penalty of $25 shall be imposed on each and every delinquent account at the time that it is physically posted for water termination.
      (2)   This penalty shall be in addition to all other penalties or costs imposed by the Township Sewer Department or the public water provider in connection with the delinquent account or the cost of turning water off or on.
   A $ 20 FEE HAS BEEN ADDED TO YOUR SEWER ACCOUNT TO COVER THE COSTS INVOLVED WITH PREPARING AND MAILING THIS DELINQUENT NOTICE.
   IF YOU FAIL TO MAKE PAYMENT IN FULL, AFTER THE WATER SUPPLY IS SHUT OFF, IN ADDITION TO PAYING THE FULL AMOUNT OF YOUR SEWER BILL, YOU WILL BE REQUIRED TO PAY:
      1   AN ADDITIONAL $125 FOR THE COSTS AND EXPENSES OF WATER SERVICE TERMINATION AND RECONNECTION, AND FOR NOTICE AND POSTING COSTS, PLUS
      2.   A MINIMUM SEWER SERVICE CHARGE CALCULATED AT THE RATE OF $32 PER MONTH, PLUS
      3.   AN AMOUNT EQUAL TO THE ESTIMATED LOST WATER REVENUES OF THE SUPPLIER, PLUS
      4.   ALL PENALTIES AND INTEREST AS ALLOWED BY LAW.
CONEMAUGH TOWNSHIP SEWER DEPARTMENT BOARD OF SUPERVISORS
Pennsylvania law provides that:
* * * In no case shall the water supply be shut off to any premises until ten days after written notice of an intention so to do has been mailed the person liable for payment of the rentals and charges, and in addition thereto, there has been posted a written notice at a main entrance to the premises. If during such ten-day period, the person liable for the payment of the rentals and charges delivers to the water utility authority or municipality supplying water to the premises a written statement, under oath or affirmation, stating that he or she has a just defense to the claim, or part of it, for such rentals or charges, then the water supply shall not be shut off until claim has been judicially determined. The statement shall also contain a declaration under oath or affirmation that it was not executed for purpose of delay.
 
(Res. R01-04, passed 5-19-2004; Res. R04-07, passed 7-18-2007; Res. R05-07, passed 10-24-2007; Res. R12-09, passed 10-21-2009)