13.16.100 Wastewater discharge permitting existing connections.
   Any significant industrial user which discharges industrial waste into the POTW prior to the effective date of this chapter, and who wishes to continue such discharges in the future, shall, within thirty days after such date, apply for a wastewater discharge permit, and shall not cause or allow discharges to the POTW to continue after sixty days of the effective date of this chapter, except in accordance with a wastewater discharge permit issued by the utility service board .
   A.   A wastewater discharge permit shall include such conditions as are deemed reasonably necessary by the utility service board to prevent pass through or interference, protect the quality of the water body receiving the treatment plant's effluent, protect worker health and safety, facilitate sludge management and disposal, and protect against damage to the POTW.
   B.   Wastewater discharge permits shall contain:
   1.   A statement that indicates wastewater discharge permit duration, which in no event shall exceed five years;
   2.   A statement that the wastewater discharge permit is nontransferable without prior notification to the city in accordance with Section 13.16.160 of this chapter, and provisions for furnishing the new owner or operator with a copy of the existing wastewater discharge permit;
   3.   Effluent limits, including best management practices, based on applicable general pretreatment standards in 40 CFR Part 403, categorical pretreatment standards, local limits, and state and local law;
   4.   Self-monitoring, sampling, reporting, notification, and record-keeping requirements. These requirements shall include an identification of pollutants to be monitored, sampling location, sampling frequency, and sample type based on federal, state, and local law; and
   5.   A statement of applicable civil and criminal penalties for violation of pretreatment standards and requirements, and any applicable compliance schedule. Such schedule may not extend the time for compliance beyond that required by applicable federal, state, and local law.
   C.   Wastewater discharge permits may contain, but need not be limited to, the following conditions:
   1.   Limits on the average and/or maximum rate of discharge, time of discharge, and/or requirements for flow regulation and equalization.
   2.   Requirements for the installation of pretreatment technology, pollution control, or construction of appropriate containment devices, designed to reduce, eliminate, or prevent the introduction of pollutants into the treatment works.
   3.   Requirements for the development and implementation of spill control plans or other special conditions, including management practices necessary to adequately prevent accidental, unanticipated, or non-routine discharges;
   4.   Requirement to control slug discharge, if determined by the utility service board to be necessary.
   5.   Development and implementation of waste minimization plans to reduce the amount of pollutants discharged to the POTW;
   6.   The unit charge or schedule of user charges and fees for the management of the wastewater discharged to the POTW;
   7.   Requirements for installation and maintenance of inspection and sampling facilities and equipment;
   8.   A statement that compliance with the wastewater discharge permit does not relieve the permittee of responsibility for compliance with all federal and state pretreatment standards, including those which become effective during the term of the wastewater discharge permit; and
   9.   Other conditions as deemed appropriate by the utility service board to ensure compliance with this chapter, and state and federal laws, rules, and regulations.
(Ord. 10-12 (part), 2010; Ord. 04-2 (part), 2004; Ord. 99-16 (part), 1999)