(A) Application submittal. An application for lot line adjustment shall be submitted to the Director with required number of copies of the lot line adjustment survey map and supporting documentation and the application fee. The Director shall have 30 working days to approve or deny the application.
(B) Review process.
(1) If necessary to accurately review the application, the Director may require additional information to be shown on the lot line adjustment map.
(2) If rejected, written notice shall be provided to the applicant via first class mail, postmarked within 15 days after the expiration of the 30-day review period along with reasons for the rejection.
(3) If denied, the written notice shall specify the reasons for denial.
(C) Appeal. Any applicant for lot line adjustment who is dissatisfied or aggrieved by the decision of the Planning and Zoning Director may appeal that decision by following the appeal process in § 153.005 above.
(D) Actions after final approval. If the application is approved, the applicant shall submit the following:
(1) A final, recordable, reproducible map meeting the requirements of § 153.132(C)(2) above, consistent with the approved plan showing all lot corners, dimensions, a complete legal description of each affected lot, and signature block for the Planning and Zoning Director, and Town Engineer;
(2) The applicant shall provide a cashier's check, certified check, or money order in the amount of the land split recording fee made payable to the Mohave County Recorder;
(3) The applicant's surveyor shall set survey monuments at each parcel corner (or line point) prior to recording the lot line adjustment map; and
(4) Upon approval by the Director, the Planning and Zoning Director shall record the lot line adjustment map with the Mohave County Recorder's Office.
(Ord. 2007-2, passed 5-29-2007; Am. Ord. 2014-02, passed 12-15-2014; Am. Ord. 2017-03, passed 11-13-2017)