§ 177.03  GRANTING PERMIT.
   After the above application is made and has been duly considered as provided by this subchapter, and upon the authority and approval of the City Council, a building permit shall be issued under the authority of the Colome City Council in the following manner: said building permit shall be conspicuously displayed upon the premises where the construction is taking place. Also attached to said building permit shall be any and all other permits which may be applicable. No construction by any owner of said premises, nor any agent, contractor or any other person, shall take place in any manner or form and no water or sewer service or other connection shall be provided until said building permit shall have been duly issued.
(Ord. 61, passed 6-2-1975; Ord. 170, passed --)  Penalty, see § 177.99