§ 53.04  IRRIGATION PLAN AND PERMIT.
   Any applicant who seeks to remove water from a storm water detention pond for irrigation purposes and to replenish the water in the storm water detention pond with a well must seek a permit from the city and provide the following information:
   (A)   Irrigation system plan;
   (B)   Detailed plan sheet showing the pumping outlet from the storm water detention pond;
   (C)   Detailed plan sheet showing the location of the well and the proposed inflow into the storm water detention pond;
   (D)   Management and maintenance plan detailing how the applicant will manage and maintain the irrigation system and the well;
   (E)   Projected annual pumping needs for the irrigation system; and
   (F)   Projected annual pumping needs for the well into the storm water detention pond.
(Ord. 162, passed 9-20-2005)  Penalty, see § 10.99