§ 152.212 CONSTRUCTION SITE POSTING.
   (A)   The developer shall post a notice near the main entrance of the construction site accessible to the public with the following information:
      (1)   A copy of the NOC with the NPDES permit tracking number for the construction project;
      (2)   Name, company name, email address (if available), telephone number and address of the project site owner/operator or a local contact person;
      (3)   A brief description of the project; and
      (4)   The location of the SWPPP (see CGP).
   (B)   The notice must be maintained in a legible condition. If posting this information near a main entrance is infeasible due to safety concerns, or not accessible to the public, the notice shall be posted in a local public building. If the construction project is a linear construction project (e.g., pipeline, highway, and the like), the notice must be placed in a publicly accessible location near where
construction is actively underway and moved as necessary. This permit does not provide the public with any right to trespass on a construction site for any reason, including inspection of a site. This permit does not require that permittees allow members of the public access to a construction site.
   (C)   The developer shall also retain following items/information in an appropriate location on-site:
      (1)   Rain gauge;
      (2)   A copy of twice weekly inspection reports;
      (3)   A documentation of quality assurance site assessments, if applicable (see CGP); and
      (4)   A copy of the site inspector's Fundamentals of Erosion Prevention and Sediment Control Level 1 certification.
(Ord. 2012-18, passed 11-12-12)