(A) Sanitary sewers. The subdivider shall provide the subdivision with a complete sanitary sewer system which shall connect with an existing approved sanitary sewer outlet. Except that when such approved outlet is not within 1,000 feet of the area being subdivided, one of the following methods of sewage disposal may be authorized by the Plan Commission:
(1) A complete sanitary sewer system to convey sewage to a treatment plant, to be provided by the subdivider.
(2) A private sewage disposal system on individual lots.
(B) Water. The subdivider shall provide the subdivision with a complete water main system, including fire hydrants meeting the requirements of the Fire Insurance Underwriters Association, which shall be connected to an existing approved public water system, except that when such an approved system is not within 1,000 feet of the area, the subdivision may provide the following”:
(1) A complete, private water supply system to be provided in accordance with the State
Board of Health requirements and fire hydrants meeting the requirements of the Fire Insurance Underwriters Association shall be installed.
(2) An individual private water supply facility must be on each lot of the subdivision. The subdivider shall show reasonable evidence that an adequate water supply is available to serve the area.
(Ord. 2011-07, passed - - )