The rate adjustment shall be applicable to all units serviced through the town’s sewage works and will be based solely on changes in the wholesale treatment rate as calculated below:
New Wholesale Treatment Rate per Thousand Gallons (update for new Fremont Treatment rate) | $10.76 |
Less: Wholesale Treatment Rate in Base Rates (set per 2022 Rate Study) | (10.76) |
Wholesale Treatment Adjustment Factor per Month | 0.00 |
Add: Monthly Treatment Base Rates (2022 Rate Study) | 10.76 |
Adjusted Wholesale Treatment Rate | 10.76 |
Multiply: Average Flow per EDU (thousands of gallons) | 3 |
Wholesale Treatment Rates per Customer per Month | 32.28 |
Add: Collection, Administrative and Other Costs (2022 Rate Study - See Table Below) | 61.84 |
Residential Bill per Month | $94.12 |
Effective Date | Other Operational Cost Allowance Per 2022 Rate Study |
May 1, 2022 | $61.84 |
January 1, 2023 | $63.16 |
January 1, 2024 | $65.16 |
Plus: | |
The cost of making the public sewer suitable for connection, including excavation, backfill, pavement replacement, and the components of the public sewer required for connection, including, but not limited to, the grinder pump. |
(Ord. 2022-02, passed 3-15-22)