Prior to the location, relocation, establishment or occupancy of any manufactured home, the owner or authorized representative shall secure a permit for the action from the Building Department as follows:
(A) Application for a permit shall be made on forms prescribed by the Town Planning Authority.
(B) The fee for a permit shall be $35. This fee is in addition to fees required for other necessary permits.
(C) Applicants shall be required to:
(1) Provide plot plans as required;
(2) Have Health Department approval for sewage disposal, water supply or gas supply system;
(3) Meet all conditions of HUD or subdivision approval, where applicable;
(4) Submit to an on-site inspection consisting, as applicable, of setbacks, anchoring system, foundation fascia, utility connections and accessory structures; and
(5) Provide the Town Planning Authority with a copy of the manufacturer’s HUD approved installation instructions, if applicable.
(Ord. 526, passed 6-8-1981)