§ 150.35 APPLICATION PROCEDURE.
   (A)   Any person desiring to commence or proceed to erect, construct, repair, enlarge, demolish, or relocate any building or dwelling, or cause the same to be done, shall file with the Village Clerk an application for a building permit.
   (B)   The application shall be in writing on a form to be furnished by the Village Clerk for that purpose.
   (C)   Every such application shall set forth the legal description of the land upon which the construction or relocation is to take place, the nature of the use or occupancy, the principal dimensions, the estimated cost, the names of the owner, architect, and contractor, and such other information as may be requested thereon.
   (D)   The application, plans, and specifications so filed with the Village Clerk shall be checked and examined by the Village Planning and Zoning Board and if they are found to be in conformity with the requirements of this chapter and all other ordinances applicable thereto, the Village Planning and Zoning Board shall authorize the Village Clerk to issue the said applicant a permit.
   (E)   This permit must be obtained ten days before any erection, construction, enlargement, demolishment, or relocation of any building or dwelling.
(Prior Code, § 9-401) (Ord. 365, passed 10-1-1985)
Statutory reference:
   Related provisions, see Neb. RS 17-550 and 17-1001