(A) On or before July 1, 1963, and at two-year intervals thereafter, the Board shall have prepared under its direction and control a four-year construction plan for the county highway system which shall go into effect on and after January 1 of the following year.
(B) The plan shall include a map of the county showing the existing county highway system and other roads and also showing the proposed new construction.
(C) The plan shall provide:
(1) All sections of the county highway system to be constructed or reconstructed in the next four years;
(2) The estimated total cost of such construction or reconstruction; and
(3) The contemplated construction date for each section to be constructed.
(Ord. 10-1-62, passed 10-1-1962)