Prior to beginning the construction of a facility, the applicant shall submit the following to the Planning Commission Office:
(A) An application in the form attached to Ord. 2023-04 as Appendix 1;
(B) An application fee in the amount of $50,000;
(C) All documents (including but not limited to facility plans and specifications) requested by Planning Commission Staff in order to demonstrate compliance with the setback provisions contained in § 156.06;
(D) A decommissioning plan to be reviewed and approved by the Planning Commission and the county for compliance with § 156.07. The decommissioning plan shall be reviewed and updated every three years by a certified independent solar facility engineer to be selected by the county, with the cost to be paid in full by the owner/operator of the facility; and
(E) The applicant shall post the bond or letter of credit as determined by the county required by § 156.07.
(Ord. 2023-04, passed 6-22-2023)