Mining of material requiring a excavation from pits or pools, provided, in addition to the requirements of § 153.076, that:
(A) A buffer strip of undisturbed land of sufficient width, as determined by an engineer, to prevent flood flows from channeling into the excavation, is left between the edge of the channel and the edge of the excavation;
(B) The excavation meets all applicable laws and regulations of other local and state agencies; and
(C) Excavated material may be processed on site but is stockpiled outside the floodway.
(Prior Code, § 11-2(9.3))
Statutory reference:
Mining of minerals in the floodway, see ARM § 36.15.602(1)(a), ARM § 36.15.602(1)(b), ARM § 36.15.602(1)(c)