§ 154.14 NOTIFICATION OF PERMIT HOLDER.
   The person to whom a permit is issued shall notify the Building Commissioner:
   (A)   Of the time of commencement of operations under such permit, 48 hours in advance of such time where excavation will enter a public right of way, and in all other instances 24 hours in advance of such time;
   (B)   Immediately of any delay in the time of commencement of which notification has been given as provided in division (A);
   (C)   When the operation is completed;
   (D)   Prior to commencement of operations, of the locations of any borrow sites or any disposal sites for excess materials.
(Ord. 1471, passed 2-6-90)